Storage Tank System Hardware Compliance Program and Tank System Removals at a Federal Site

XCG was retained to complete a storage tank compliance audit at a Federal site. The audit completed by XCG found that there were a number of significant risks, mainly associated with the locations of the storage tank systems on a wharf located on Lake Ontario. The storage tank   systems were comprised of one diesel aboveground storage tank (AST) (7,600 L), one gasoline AST   (2,270 L), and one waste oil AST (500 L). Consequently, the Client decided that the tank   systems were to be removed. As such, XCG was able to develop tender drawings   and specifications for their removal as well as a Class ‘A’ cost estimate.


As   part of the decommssioning project, XCG conducted a pre-demolition level designated substances and hazardous materials survey  (DSHMS), provided oversight during tendering/bidding phase and throughout the  project, and was involved with Contractor oversight during the removal of the   fuel systems.


The diesel, gasoline, and waste oil   ASTs and all related equipment were removed from the subject site by a   qualified contractor that is certified by the Technical Standards &   Safety Authority (TSSA). Prior to removal, all of the ASTs’ contents were   removed from the ASTs along with their associated piping and equipment.   During the petroleum product transfers, deployable spill containment measures   were used at all times ensuring that no spills or releases occurred during   decommissioning activities. Additionally, all vapours were purged using the   dry ice method from the ASTs prior to dismantling. The ASTs were all vapour tested prior to transport. The ASTs were removed by an approved person and   disposed of in accordance with the contract specifications and applicable   provincial/federal regulations.


XCG demonstrated our ability to provide   Contractor oversight and to adhere to both Provincial and Federal health and safety regulations and applicable codes regarding fuel handling and the decommissioniof fuel storage systems.

© 2021 by XCG Consulting Limited

KITCHENER OFFICE

820 Trillium Drive,

Kitchener On, N2R 1K4

519-741-5774

KINGSTON OFFICE

Suite 102 - 4 Cataraqui Street,

Woolen Mill, East Wing

Kingston On, K7K 1Z7

613-542-5888

EDMONTON OFFICE

#200, 6768 - 75th Street,

Edmonton Ab, T6E 6T9

780-432-5770